We worked on the 5.5km dual carriageway, which provided the long awaited bypass for Kingskerswell. The road now bypasses the existing A380, between Newton Abbot and Torbay.
We were contracted to lay up to 1000 tonnes per day of CBM and Asphalt. The 5 month contract required the supply of two gangs, one site Supervisor and all equipment. The contract saw the first outing for our Volvo paver which can lay CBM at a width of 7.5m.